The construction project at the main La Fuente Riviera campus has been a tremendous undertaking. Due to conservative money management and generous donors, we have been able to remain totally debt free through the process of construction.

Progress

The construction has been broken into three phases. 1) kitchen, dining room, & classrooms 2) upstairs offices, multipurpose room, & dormitories 3) main sanctuary

Phase 1 broke ground on February, 2010. Within a year, the kitchen, dining room, and classrooms were fully functional. These resources have been invaluable as our kids’ program continues to grow.

Phase 2 is nearing completion now. The roof was poured in August 2011. The walls are being stuccoes and will soon be ready for flooring and paint. Some of the offices upstairs have been occupied since October, when the old office building was demolished to make way for Phase 3.

Phase 3 is in the preliminary stages. The foundation is ready and the support pillars for the roof are in place. The goal is to be able to meet in the sanctuary by summertime.

Foot x Foot

We still need your help! Due to several generous supporters, we are ready to move forward, but we still do not have everything we need to finish the project. We have estimated that only $50.00 USD will pay for 1 square foot of finished construction. Please prayerfully consider supporting our ministry as we move forward to make disciples in Mexcio.